On Nov. 18 the Army posted two documents to its installation notices page: an Environmental Assessment for "Lead Azide Risk Mitigation" and a Mitigated Finding of No Significant Impact (Army notifications). An Environmental Assessment is the review federal agencies write to decide whether a project needs a full environmental impact statement. The finding says it does not, as long as the listed mitigations happen (Army FONSI).
We read the Assessment. Here is what it says, with section references so you can check them yourself (Army EA).
Why the Army says it has to act
The stated purpose is to dispose of a degraded lead azide stockpile permanently by detonating it where it sits, while controlling blast pressure, noise and the spread of contamination. The need, in the Army's words, is that the material poses "an unacceptable explosive safety risk" to plant workers, buildings and surrounding operations. The Assessment says the material has recrystallized, cannot be moved safely, and that explosive ordnance disposal experts recommended disposal in place (sections 1.2 and 1.1) (Army EA).
It says the problem was identified in a March 2026 safety review and the material was reclassified as hazardous waste that month, with waste codes for reactivity and for lead toxicity (sections 1.1 and 3.5.2) (Army EA).
The alternatives, and why each lost
- Do nothing. Rejected as not viable: crystallization and accident risk would continue, the plant would stay out of compliance with hazardous waste law, and access restrictions would drag on. It is kept only as a baseline for comparison (section 2.2.3).
- Chemical neutralization. Eliminated because it would require prolonged hands-on handling of the drums over 7 to 22 operating days, with uncertain success (section 2.2.4).
- Move it to the plant's open detonation range. Eliminated because moving the drums carried an unacceptable risk of accidental detonation (section 2.2.4).
- Detonate without mitigation. Eliminated because it would spread airborne lead in a way that violates hazardous waste rules and defense standards (section 2.2.4).
- Mitigated controlled detonation. Chosen, mainly because it minimizes handling and provides a regulated cleanup path (section 2.2.2).
All of this is from the Assessment itself (Army EA). For outside criticism of the alternatives analysis, see our report on the alternatives the Army rejected and the lawsuit against the permit.
The air model: worst case, and no numbers
The Assessment describes preliminary plume modeling by the Interagency Modeling and Atmospheric Assessment Center, a federal center that models hazardous releases. That model assumed a worst case with no mitigation. Under some weather conditions, it says, concentrations "could exceed" PAC-1, the lowest tier of emergency exposure guidelines, which corresponds to mild, temporary and reversible effects. It says the model shows concentrations would not reach PAC-2 or PAC-3, the tiers tied to more serious effects (section 3.3.4) (Army EA).
What it does not give: any actual concentration, any distance where PAC-1 might be exceeded, or a comparison with the federal air quality standard for lead. It says only that the event will not change Des Moines County's attainment status for that standard. Final modeling with mitigations and a separate air monitoring plan are described as still to come (sections 3.3.4 and 3.3.5) (Army EA). For how to read the maps the Army has published since, see our plume map explainer.
The weather rules
The Assessment sets go or no-go conditions checked by on-site weather stations: no precipitation, surface winds of 15 mph or less, no thunderstorms and no temperature inversion. The work is to happen in daylight (sections 2.1 and 3.3.5) (Army EA). These rules help explain why the date has already moved once. The Army's Nov. 19 notice moved the blast to Monday (Army notice); see our report on the cold-weather reasoning.
The mitigations
- Water cannons or misters to wet the magazines, barriers and ground before the blast and during cleanup (section 3.3.5).
- Sand- and lime-filled barriers around each of the two earth-covered magazines, built in 1940, with blast energy vented to the south and southwest (sections 2.1, 3.7.4 and 3.8.2).
- A 6,269-foot exclusion zone for nonessential people; homeowners inside it are notified and asked to leave (sections 3.2.5 and 3.10.4).
- Fire crews staged outside the blast arc, brush cleared, and silt fencing and berms to catch runoff (sections 2.1, 3.6.5 and 3.9.5).
- Baseline sampling of soil, surface water, sediment and existing groundwater monitoring wells before the blast (sections 3.3.2 and 3.6.2).
Source for all of the above: Army EA.
The cleanup commitments
After the blast, the Assessment says crater soil and debris will be tested for lead. Debris that fails a standard leaching test, set at 5.0 milligrams of lead per liter, is handled as hazardous waste; debris that passes can go to an ordinary landfill. Soil above EPA's screening level for lead is to be dug out until confirmation samples meet cleanup goals, then backfilled with clean soil. Surface water and groundwater are to be sampled again and compared with the baseline, and a closure report goes to EPA (sections 3.2.5, 3.5.4 and 3.6.4) (Army EA). The emergency permit separately requires sampling, cleanup and reporting (EPA).
Off the plant, the Assessment mentions post-blast soil sampling of the nearest farm fields among about 6,400 acres of agricultural leases (sections 3.10.2 and 3.10.4) (Army EA). The Intercept reported that the Army's October open house handout said sampling on private property happens only with the owner's permission (The Intercept).
What the document leaves out
- How much lead azide. The Assessment refers to drums but gives no count or weight (Army EA). The figures in news coverage, 68 barrels and about 9,500 pounds, come from Army statements and reporting, not this document. See What is lead azide?
- Numbers for the plume. No concentrations, no distances.
- Window damage. It discusses window damage only for the do-nothing scenario, where an accidental blast would "likely" exceed 140 decibels at the boundary. For the planned blast it says the event "will be audible off-post" and the barriers will reduce noise to a level that minimizes complaint or damage risk, without a predicted level (sections 3.4.3 and 3.4.4) (Army EA). The Army's own advisory warned of possible localized window damage in Middletown (Army advisory).
- Residents' property. Claims, private wells, gardens, pets and livestock are not addressed. Groundwater monitoring covers only existing wells on the installation (Army EA). We cover each of those in separate guides linked below.
- Public comment dates. It says comments will be considered and cites an Oct. 15 open house, but gives no comment period or deadline (sections 1.3 and 2.1) (Army EA).
Our reading of the Assessment was done the day after it was posted. If the Army releases a revised version or the final plume model, we will update this report.