The $635 Million Artillery Plant Next Door to the Lead Azide

The Army broke ground on a new 155mm shell factory at the same plant this summer. Its own environmental assessment cites ammunition production as a reason not to leave the lead azide alone.

By . Published . 4 min read.

Two very different Army projects are happening on the same 19,000 acres this year. One is a brand-new, highly automated artillery shell factory. The other is a pile of decades-old explosive that has to be blown up. The Army has mostly talked about them separately. They are not entirely separate.

The factory

In August 2025 the Army announced a $635 million investment to design, build and commission a Future Artillery Complex at the Iowa Army Ammunition Plant (U.S. Army). The contract went to MSM Group North America, part of the Czechoslovak Group, according to reporting that cited Axios (AOL). It is designed to load up to 36,000 155mm artillery rounds a month (Army Technology).

On July 15, 2026, the Army broke ground, with Gov. Kim Reynolds attending. The complex will replace the plant's World War II-era M795 artillery production line, which the Army says is nearing the end of its operational life (U.S. Army). Construction is expected to take about 40 months (Interesting Engineering).

Why the rush? Demand for 155mm shells has soared since Russia invaded Ukraine in 2022, and the Army wants to reach 100,000 rounds a month nationally (Axios, Defence Industry Europe).

Where the two stories meet

The Army's environmental assessment considered leaving the lead azide in storage. It rejected that option because the material could explode accidentally and indefinitely disrupt the plant's ability to make new ammunition, The Intercept reported after reviewing it (The Intercept).

That is a legitimate concern. An accidental blast at a working ammunition plant would be a disaster for workers and for the region. But it means the disposal decision was weighed partly against production, not only public health. That is worth saying out loud.

The March shutdown also hit right as construction was starting. A notice at the time gave advance warning of construction activity for the Future Artillery Complex beginning that month (Des Moines Register).

What the Army says

An Army spokesperson said the 155mm facility is on the other side of the plant from the lead azide and that the Army anticipates a four-hour delay to construction on detonation day (syndicated report). In other words, the Army does not expect the blast to hurt the new plant.

What we are not saying

We have found no document showing the lead azide timeline was set to suit the construction schedule. The Army says the Monday date was chosen to beat a cold snap. The groups suing EPA have not alleged a link either. Anyone claiming the blast is happening for the factory's benefit is going beyond the evidence.

The fair point is narrower. The federal government is about to spend hundreds of millions to expand explosives production at a contractor-run Superfund site, at the same moment that site is dealing with a stockpile that went bad on someone's watch. Eight officials from both parties, including members of Congress and the governor of Illinois, already asked the Army to examine the contractor's handling of hazardous material (KWQC). Before the new line opens, residents deserve to know what changes so this does not happen again.

Share this report

Quick answers

What is the Future Artillery Complex?

A new 155mm artillery shell loading facility at the Iowa Army Ammunition Plant, funded by a $635 million Army contract and designed to load up to 36,000 rounds a month.

When did construction start?

The Army broke ground on July 15, 2026. Construction is expected to take about 40 months.

Is the new artillery plant connected to the lead azide detonation?

They are on the same installation. The Army's assessment rejected leaving the lead azide in place partly because an accident could disrupt ammunition production. The Army says the new facility is on the other side of the plant.

Will the detonation affect construction?

An Army spokesperson said the Army anticipated a four-hour construction delay on detonation day.

Sources

  1. Army invests $635M in cutting-edge artillery ammunition production facility, U.S. Army, Aug. 20, 2025
  2. Army reportedly greenlights plans for massive ammo factory, AOL
  3. US Army 155mm ammunition, Army Technology
  4. Army breaks ground on state-of-the-art ammunition plant in Iowa, U.S. Army, July 22, 2026
  5. Explosive loading facility for 155mm ammunition, Interesting Engineering
  6. Army kickstarts plans for huge artillery ammo factory in Iowa, Axios, Aug. 20, 2025
  7. CSG breaks ground on Future Artillery Complex, Defence Industry Europe
  8. Just rinse it off, Army says, The Intercept
  9. Iowa ammunition plant temporarily closes, Des Moines Register via Yahoo
  10. The US Army needs to get rid of old explosives near its new artillery ammo plant, DNYUZ (syndicated)
  11. Bipartisan lawmakers call for delay, KWQC

Every factual claim in this report links to its source. If you find an error, send a correction and we will fix it and note the change here.